A System of Empty Promises

An evidence-led timeline of ECO4’s broken safeguards – what was promised, what best practice demands, and what actually happened

Is this what ‘quality assurance’ looks like?

Months of TrustMark complaint and no action
+
Bodies overseeing one home / install, in conflict with the PAS ‘whole home approach’
%
Up to a 98% failure rate
Zero protection where bills go up, not down, under the premise of a scheme designed to alleviate fuel poverty.

The Promise

  • “Consumer safeguards” through TrustMark registration
  • Quality assurance via audits and standards
  • Fraud controls and working groups
  • Clear routes to “redress”
  • Public Accounts Committee assurances that “all homes will be put right” – not just those with EWI
  • “Warm Homes Plan” overhaul

The Reality

  • Devolved and deflected accountability
  • The injustices of absent protection every bit as great as a failed install
  • Ignorance of Solar PV and Heat Pump failure, including higher bills
  • The priority of process and profit over people
  • Empty assurances in lieu of meaningful actions
  • A scheme capable of worsening lived experience, rather than improving it
  • Many ECO4 victims are unaware of what a Retrofit Coordinator actually is

We Believe a Full and Urgent Independent Review of ECO4 is Now Needed, Alongside Referral to the Serious Fraud Office

Each item below contains the same four fields: Date, Promise, Best practice, Reality.

Empty Promises Since 2016

2016

x

The Promise

“Each Home Counts” reform lineage is held out as the basis for improved consumer protection/quality assurance.

Best Practice

Single point of accountability; enforceable consumer remedies; transparent reporting on failures and sanctions.

The Reality

A decade later, the NAO is still documenting widespread non-compliance, fraud exposure, and a fragmented oversight model.

Unskilled Labour Completing Highly Skilled Works

2022 – 2026

The Promise

The governance of ‘whole home’ retrofit under a comprehensive system of standards and accreditation

Best Practice

Every individual on a jobsite should be accredited, insured, and their registration details made available to the homeowner.

The Reality

Firms grow rapidly by hiring poorly skilled and unverified 3rd party contractors often with no formal qualifications. They fire as quickly as they hire.

2016

x

The Promise

“Each Home Counts” reform lineage is held out as the basis for improved consumer protection/quality assurance.

Best Practice

Single point of accountability; enforceable consumer remedies; transparent reporting on failures and sanctions.

The Reality

A decade later, the NAO is still documenting widespread non-compliance, fraud exposure, and a fragmented oversight model.

Inadequate Fraud Controls

June 2024

The Promise

DESNZ establishes a fraud working group (DESNZ/Ofgem/TrustMark) in response to TrustMark’s concerns.

Best Practice

Fraud controls should be “always on”: independent verification, rapid sampling, evidence preservation, public reporting, and immediate enforcement triggers.

The Reality

NAO later records structural incentives to overclaim and scheme weaknesses exposing ECO4 to fraud/error/gaming/non-compliance.

Weak fraud controls are introduced 3.5 years into a 4-year scheme.

Process First, not People First

July 2024

The Promise

TrustMark is first notified of my own emergency situation in July 2024; seriousness/severity is acknowledged.

Best Practice

Site visit within 7 days max, systems-led audit, and a formal remediation order with urgent timelines and clear penalties.

The Reality

No decisive action/outcome for ~18 months: “almost 18 months since notifying TrustMark… still no clarity… aware of the severity.”

The ‘Assurance’ Facade

We have reason to believe TrustMark were aware well before Nov 2024, in contrast with the assurances made at the Public Accounts Committee held 13th November 2025

Nov 2024

The Promise

TrustMark raises concerns about non-compliant IWI; DESNZ sets up a workstream to understand extent and identify remediation options.

Best Practice

Precautionary pause on high-risk measures; independent inspection surge; remediation plan before continuing volume delivery.

The Reality

NAO shows the first statistically representative estimate of scale only arrives later (Aug 2025), i.e., harm precedes certainty and control.

Focus on Political Risk, not Risk to Health and Homes

Dec 2024

The Promise

DESNZ asks certification bodies to audit 20% of EWI installs.

Best Practice

100% audit of high-risk measures; independent auditors; publish failure rates by installer/scheme provider; rapid suspensions.

The Reality

Even with escalations, NAO documents major non-compliance and cases with immediate health and safety risk.

Solid Wall-only Inspections, Reliant on Proactive Homeowners

Jan–Feb 2025

The Promise

Ofgem writes to ~60,000 households; helpline provided; audits and remediation tracking.

Best Practice

Each household gets a case owner, enforceable timelines, and funded remediation pathways—not “signposting”.

The Reality

NAO record shows limited high-priority triage volumes and extended audit programmes to understand scale. c.9000 / 11000 homes found to be faulty.

NAO Report Fails to Address all High-Risk Measures – Only Those that are Politically Convenient

May 2025

(NAO timeline item)

The Promise

A DESNZ-commissioned report finds the scheme is significantly exposed to fraud/error/gaming due to weaknesses in design/operation/oversight.

Best Practice

Automatic redesign of scheme controls; enforceable gatekeeping; independent verification of eligibility and outputs.

The Reality

Later ministerial correspondence still describes a system where oversight is diffuse and consumer resolution difficult.

TrustMark Responsible for a 3rd Winter in the Cold

Sept 2025

TrustMark dispute comms

The Promise

After failing to record a prior inspection, TrustMark confirm – after over a year of complaint – that they will attend my home; engage with MCS; review heat loss calculations.

Best Practice

Independent inspection promptly, with clear scope, published methodology, and immediate interim safeguarding.

The Reality

An incomplete and opaque Subject Access Request, failure to provide transparency as to process and standards applied. Refusal to receive or analyse homeowner evidence.

Still awaiting the outcome of a straightforward inspection, which could be definitive within 1 hour onsite, resulting in an avoidable 3rd Winter in the cold.

Months of ‘Oversight’ Abstracted from Moments of Reality

Oct 2025

TrustMark ‘process’

The Promise

TrustMark describes visits aimed at “verify the factual timeline” to build “fact-based picture moving forward.”

Best Practice

Outcome-focused enforcement: assess compliance against PAS/MCS/Building Regs; issue determinations; compel remediation.

The Reality

The framing centres chronology/process; not a decisive enforcement posture visible in the record excerpt.

Minister Assurance: Gov has Duty of Care

5th Nov 2025

Official Correspondence

The Promise

Government duty to “safeguard consumers”; officials + TrustMark “here to help”; independent assessor visit; “expect TrustMark to assist… remediation”; overhaul promised via Warm Homes Plan.

Best Practice

Immediate enforceable action: temporary accommodation support where needed; remediation instruction; deadlines; public accountability.

The Reality

Subsequent correspondence indicates continued waiting for reports/audits; the case remains unresolved in the period covered.

Communications Protect Government, not Homeowners

5th Jan 2025

Official Correspondence

The Promise

“Protections in place”: TrustMark installers; QA oversight “including auditing of up to 10%”; routes to redress; acknowledges fragmentation; again promises “sweeping overhaul” via Warm Homes Plan.

Best Practice

If protection is real, it is measurable: high audit coverage for risk, open outcomes, fast adjudication, and compensation where harm occurs.

The Reality

MCS states it is not accredited to handle complaints and that outcomes aren’t shared with consumers; dispute framing is procedural and excludes compensation.

Meetings Promised but Never Materialise

5th Jan 2025

Official Correspondence

The Promise

Between TrustMark and DESNZ, I have received no fewer than 6 seperate assurances of meetings with officials and have sent many requests in light of the urgent plight of homeowners in receipt of ECO4

Best Practice

The transition to greener energy must be a “just transition”. ECO4 excludes and depricates homeowners by design. In constrast, customer-led design also results in more sustainable outcomes for schemes and shareholders.

The Reality

Despite representing over 300 homeowners affected by poor and shoddy work under the ECO4 grant scheme, no meetings have materialised.

TrustMark MLA and Code of Conduct are Meaningless

——–

TrustMark Master Licence Agreement

TrustMark Code of Conduct

The Promise

Master Licence / Code of Conduct language implies proactive standards, assurance, and consumer-facing integrity obligations.

Best Practice

Governance must translate into action: transparent determinations, sanctions, remediation orders, and consumer updates with evidence.

The Reality

The communications record includes explicit limitations (“not a technical specialist”), prolonged handling, and repeated requests for transparency and urgency.

Retrofit Coordinator Obligations Absent and Unenforced

Sep–Oct 2025

RC / monitoring & evaluation

ECMK Communications

The Promise

Retrofit Coordinators are present to oversee the Retrofit process in the homeowner interest, ensuring a high level of quality is delivered and that ECO4 measures are appropriate.

Best Practice

RC function should be independent in substance, not just wording; no procedural hurdles that delay safeguarding.

The Reality

The communications record includes explicit limitations (“not a technical specialist”), prolonged handling, and repeated requests for transparency and urgency in light of uninhabitable conditions – all of which go ignored in practice.

Inconvenient Expert Evidence is Ignored and Buried

Jan 2026

Expert evidence – Part35 Compliant

The Promise

A system of Quality Assurance designed to protect homeowners. (date on report page excerpt)

Best Practice

Part35-compliant technical inspection, according to PAS2035, MIS, and Building Regulations

The Reality

TrustMark refusal to accept any evidence that is not of their own or the installer’s making. TrustMark act as a trade association, rather than for the purposes of consumer protection